08/28/2026 | Press release | Distributed by Public on 08/28/2026 13:04
Location: 2878 Windsor Street, between London and Edinburgh streets
Date: Monday, Aug. 31
Time: 9 a.m. to 4 p.m.
Work details: This work is to facilitate the installation of a natural gas service pipeline.
Traffic impact: One lane of traffic will be maintained at all times. Peak hour restrictions will be in effect. Drivers should expect delays due to stop-and-go traffic and are asked to use alternative routes where possible.
Sidewalk impact: The adjacent sidewalk will be closed. Signed pedestrian detours will be in place.
Transit impact: Two of the bus stops at Windsor Street will be closed. Please visit our website for up-to-date impacts to Halifax Transit routes and bus stops.
Active transportation impact: The adjacent bicycle lane will be impacted.