The Connecticut Department of Transportation (CTDOT) is announcing that work on the Replacement of bridge carrying I-91 over Grape Brook in Enfield. This project is scheduled to begin on Monday, April 6, 2026, and be completed on Thursday, November 25, 2027. The project 0048-0200 consists of replacing the existing 12-foot-10-inch-wide by 8-foot-3-inch-high corrugated metal plate arch with a 12-foot-wide by 10-foot-high precast concrete box culvert.
New endwalls and flared wingwalls founded on spread footings will be constructed at the inlet and outlet of the culvert. Temporary construction access roads will be constructed off I-91 at both the upstream and downstream ends of the structure. It is anticipated that construction will be performed in five stages; a pre-stage, three stages installing approximately one-third of the proposed precast concrete box culvert during each stage and a post stage. Three lanes of traffic in both directions of I-91 will be maintained during construction.
CTDOT Project No. 0048-0200 was awarded to Waters Construction Company, Inc. at a cost of $13,724,834.65 on January 8, 2026, and is scheduled to be completed November 25, 2027. This project is administered by the Bureau of Engineering and Construction, Office of Construction, District 1 in Rocky Hill.
LANE CLOSURE INFO
There will be shoulder closures on I-91 leading up to and after Grape Brook starting Monday, April 6, 2026, to Thursday, November 25, 2027, during the hours of 9:00 a.m. to 3:00 p.m. and lane closures from 8:00 p.m. to 6:00 a.m. Traffic control signing patterns and State Troopers will guide motorists through the work zone.
Motorists should be aware that modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving in this area.