BRADLEY COUNTY SR-2 (S. LEE HWY.) Utility Work both directions from LM 8.12 to LM 8.14: Flagging-assisted lane closures on SR-02 (South Lee HWY) between Victory St. SW and Old Boyd Farm RD. SW Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 04/02/2026 through 05/13/2026 from 9 am - 2 pm [2025-930]
BRADLEY COUNTY SR-74 (SPRING PLACE RD.) Utility Work both directions from LM 11.07 to LM 11.14: Flagging-assisted lane closures on SR-74 (Spring Place Rd) between Clayton LN and Durkee RD SE. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 12/18/25 through 06/18/2026 from 9 am - 2 pm [2025-736]
BRADLEY COUNTY SR-74 [11.445-11.83] from Whaley Road to SR-60 APD-40 drainage improvements: During this reporting period, the contractor will continue storm drain installation and grading work on SR-74. Intermittent flagging operations and shoulder closures will be necessary periodically. Motorists should use caution and reduce speed when traveling through the work zone.
[APAC - Atlantic, Inc./Cleveland/CNZ243]
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY The installation of Weigh-in-Motion technology at 28 sites on various Interstate and State Routes: No Region 2 Lane Closures this week on CNX913. [Davis H. Elliot Construction Company, Inc./Maint - R2/CNX913]
COFFEE COUNTY I-24 (MM 117) construction of an overpass carrying Wattendorf Memorial Highway/AEDC Road, including grading, drainage, retaining walls, and paving: Drivers can expect short-term flagging operations for trucks entering and exiting the work zone on Wattendorf Highway. Please use caution when traveling through the work zone.
[Jones Bros. Contractors, LLC/Tullahoma/CNZ029]
COFFEE COUNTY SR-2 (HILLSBORO HWY.) Utility Work both directions at LM 19.34: Flagger-assisted lane closures on SR-2 (Hillsboro HWY) between Willow Oak Rd and Love Lane Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 05/06/2026 from 9 am to 2 pm [2025-1003)
COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 2 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Lanes will be reduced from 3 lanes to 2 with one lane in each direction throughout the project length. Drivers can expect intermittent flagging operations for construction operations and vehicles entering and exiting the work zone.
[Dement Construction Company, LLC/Tullahoma/CNX912]
CUMBERLAND COUNTY I-40 Utility Work both directions from MM 316.9 to MM 327.0: Law Enforcement-assisted rolling roadblock between Westbound LM 327.0, nearest EXIT 329 and Eastbound LM 316.9, nearest EXIT 317. Message boards, signage, and law enforcement vehicles will be present. Motorists should be aware of personnel and equipment, reduce speed, and be prepared to stop. 05/10/26 between 6:00 am and 9:00 am, with a rain date of 05/17/26. (2026-077)
CUMBERLAND COUNTY I-40 [304.4-306.6] from MM 304.4 to MM 306.6 bridge repair and resurfacing: Construction continues within the median of I-40. Traffic has been shifted along the project route. Motorists should use caution in the area and be aware of construction vehicles entering and exiting from the work zone. [Rogers Group, Inc./Crossville/CNZ290]
CUMBERLAND COUNTY SR-24 [0-0.16] from Putnam County Line to C189 bridge repair: The contractor continues working on the bridge repair on I-40 at MM 304.6 or SR-24 at LM 0.24. The contractor has reduced SR-24 to one lane with temporary signals. Motorists should use caution in the area. [Rogers Group, Inc./Crossville/CNZ290]
CUMBERLAND COUNTY SR-24 [15.056-15.56] from Crossville city limits to Seventh-Day Adventist Church and School bridge replacement: The contractor has closed SR-24 at LM 15.06 to LM 15.6. This closure will remain in place for the duration of the project. The posted detour is along SR-462 and SR-1. The contractor will be working on general clearing activities and utility work initially. Once initial work is completed, the Contractor will proceed with the replacement of the bridge over the Obed River. Motorists should use caution and utilize the posted detour. RESTRICTIONS: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
[Mid-State Construction Company, Inc./Crossville/CNZ206]
CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. The contractor has closed Freedonia Road. A detour has been posted to utilize Maynard Road. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution when traveling through the work zone as traffic patterns change.
[Jones Bros. Contractors, LLC/Crossville/CNV009]
CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor has shifted traffic to phase 2 on the newly constructed portions of SR-28 LM 0.90 to 1.98 in Fentress County. Work will proceed on the existing alignment of SR-28. Flaggers are being used intermittently as needed to control traffic through the work zone. Motorists are encouraged to use caution, be aware of new traffic signs and pavement markings, and watch for construction equipment and personnel throughout the project.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]
DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor is continuing work near the intersection of SR-26 and SR-53. During this work, lane closures may be used, and flaggers will be present to facilitate the flow of traffic through the work zone. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Twin K Construction/Cookeville/CNV012]
DEKALB COUNTY SR-26 [15.9-20.3] from Near Old Snow Hill Road to West of Curtis Road resurfacing: The contractor is scheduled to begin concrete curb work starting 05/04/26. During this work, the contractor will have one lane closed in each direction. Motorists should be prepared to stop as they approach the work zone, and they should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/262008]
DEKALB COUNTY SR-56 (COOKVILLE HWY.) Utility Work both directions from LM 15.38 to LM 17.32: Flagger-assisted lane closures on SR- 56 (Cookeville HWY) between Craft Center DR and Hurricane Bridge. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/30/2026 through 08/28/2026 from 9 am to 2 pm [2025-216)
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: No interstate ramp/lane closures are scheduled for this period, but the contractor may utilize traveling/moving operations to vacuum and clean debris from medians and shoulders on areas of I-75 from Exit 1 (East Ridge) to Exit 3 (East Brainerd Road) and on I-24 from Germantown Road to the I-75 Interchange as part of the final punch list. Some minor off-peak (9 AM to 3 PM) temporary lane closures may occur Monday through Friday on North and South Terrace for the contractor to perform other final punch list work. It may also be necessary to do short-duration (15 to 30 minutes) rolling roadblocks during the day or night for patching potholes, clearing debris or repairing guardrail, attenuators, etc.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound and I-75 southbound, Shallowford Road entrance ramps, and Shallowford Road exit ramps and Hamilton Place Mall exit ramp. Hamilton Loop Road is closed for retaining wall construction and storm drainage installation between the intersections near Markman's Jewelers and Texas Roadhouse. Beginning 05/11/26 through 5/12/26, the contractor will close 2 right lanes between 8 PM and 6 AM on I-75 SB from MM 8.8 to MM 6.6 for the installation of overhead signs. Additionally, following the installation of vertical sign elements, the contractor will remove the lane closures and commence rolling roadblocks to mount the overhead sign. The remaining 2 nights are in case of adverse weather. The speed limit has been reduced on I-75 throughout the project limits. Nightly lane closures are permitted 8 PM to 6 AM. Motorists should use caution, paying attention to construction signage and watching for construction vehicles and personnel.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work both directions at LM 14.81: Flagger assisted lane closures on SR-11 (Brainard rd.) from Greenway View Dr. to Old Mission Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/16/2026 through 04/23/2026 with a rain date of 04/24/2026 through 05/01/2026 from 9 am - 2 pm [2026-165]
HAMILTON COUNTY SR-2 (BROAD ST.) Utility Work both directions at LM 5.92: Flagger-assisted lane closures on SR-02 (Tennessee Ave.) Between Broad St. and W. 38th St. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/30/2026 through 05/05/2026, from 9 am - 2 pm [2025-768)
HAMILTON COUNTY SR-2 (CUMMINGS HWY.) Utility Work both directions at LM 2.31: Flagger-assisted lane closures on SR-02 (Cummings HWY) between Francis St and the I-24 overpass. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,05/07/2026 through 06/18/2026 with from 9 am - 2 pm [2026-069)
HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work both directions from LM 21.13 to LM 24.42: Flagger-assisted lane closures on SR-2 (U.S. HWY 64) between Dance Hall Rd. and Ooltewah Georgetown Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 05/07/2026 through 05/28/2026 from 9 am - 2 pm [2026-209]
HAMILTON COUNTY SR-2 [11.86-11.63] from McCallie Tunnel to McCallie Tunnel Maintenance: The McCallie Tunnels will be cleaned 05/20/2026 from 8 PM to 6 AM, weather permitting. The contractor will clean one side at a time and flag traffic during the work. Motorists should expect delays. [Diamond Specialized, Inc./Chattanooga West/CNZ133]
HAMILTON COUNTY SR-27 [5.51-7.93] from I-24 to Georgia State Line resurfacing on US-27: The contractor will have nighttime lane closures of Rossville Blvd - SR-27 between I-24 and the Georgia State Line. The lane closures will be Sunday through Thursday between the hours of 8 PM and 6 AM. At least one lane in each direction will be open to normal traffic. All on-street parking will be suspended during the nighttime work. Park accordingly and plan to move vehicles before the hours listed above. Vehicles left in the work zone during working hours will be towed at the owner's expense. The contractor will also have daytime lane closures at the intersections of East 28th St, East 32nd St, East 37th St, and East 48th Street. The contractor will be closing one lane of traffic in each direction while making needed improvements to these intersections.
[APAC - Atlantic, Inc./Chattanooga East/CNZ184]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions from LM 5.17 to LM 5.21: Flagger-assisted lane closures on SR-319 (Hixson Pike) from Austin Rd to Adams Rd. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present,04/21/2026 through 05/02/2026, with a rain date of 05/03/2026 from 9 am - 2 pm [2026-673)
HAMILTON COUNTY SR-8 (W. MAIN ST.) Utility Work both directions from LM 7.91 to LM 8.05: Flagger-assisted lane closures on SR-08 (West Main St) from Williams St. to Adams St. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present, 04/17/2026, with a rain date of 05/24/2026 from 9 am - 2 pm [2026-150)
HAMILTON COUNTY SR-8 [11.67-11.75] Stringers Ridge Tunnel Cleaning: The Stringers Ridge Tunnel will be closed 05/20/2026 from 8 PM to 6 AM for cleaning. A detour will be in effect during the closures to direct traffic to alternative routes. This work is weather permitting. [Diamond Specialized, Inc./Chattanooga West/CNZ133]
HAMILTON COUNTY SR-8 [5.04-5.27] Bachman Tubes Tunnel Cleaning: The Bachman Tunnel will be closed 05/21/2026 from 8 PM to 6 AM for cleaning. A detour will in effect during the closures to direct traffic to alternative routes. This work is weather permitting.
[Diamond Specialized, Inc./Chattanooga West/CNZ133]
JACKSON COUNTY SR-53 [17.46-17.6] from south of Hurricane Branch to Near Hurricane Branch Lane culvert replacement: SR-53 is now open to traffic. Motorists are encouraged to drive through the work zone with caution as there will be times where intermittent flagging operations will be utilized as the contractor completes the project.
[Cleary Construction, Inc./Livingston/CNZ250]
MARION COUNTY I-24 TDOT Contractor eastbound from MM 140.6 to MM 165.7: Big Woody's Tree Service will be performing mechanical tree and brush removal 05/07/26 - 05/13/26 from 7 AM to 5 PM. Big Woody's will be closing shoulder in the East bound direction.
MARION COUNTY I-24 TDOT Contractor westbound from MM 156.4 to MM 141.1: Big Woody's Tree Service will be performing mechanical tree and brush removal 05/07/26 - 05/13/26 from 7 AM to 5 PM. Big Woody's will be closing shoulder in the West bound direction.
MARION COUNTY I-24 [137-138.2] from 137 to 138.2 Rockfall Mitigation on I-24 near MM 137: The contractor will be performing rockfall mitigation operations on I-24 WB beginning at MM 138.2 in Marion County. The middle lane, right lane, and right shoulder have been closed. 2 Lanes of traffic have been shifted to flow on the left shoulder and left lane. All lanes will be reopened to traffic by May 22, 2026. Work will continue off the road after May 22, and the project will be completed by July 31, 2026. [Summers-Taylor, Inc./Dunlap/N262018]
MARION COUNTY SR-108 [2.8-3.24] slide mitigation: The contractor will be performing slide mitigation operations, including grading, drainage and paving on SR-108 in Marion County at LM 2.8. The roadway will be reduced to one lane controlled by temporary traffic signals. The project completion date is 08/31/2027. Please use caution when driving through the work zone.
[Wright Brothers Construction Company, Inc./Dunlap/CNZ226]
MARION COUNTY SR-150 (US-41) Utility Work both directions at LM 11.38: Flagger-assisted lane closures on SR- 150 (US HWY 41) between Mossy Oak Dr and Cumberland Trails RV Park. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/30/2026 from 9 am to 2 pm with a rain date of 05/01/2026 [2026-200)
MARION COUNTY SR-2 [17.2-17.3] from 17.2 to 17.3 construction: The contractor will be performing grading and drainage operations on SR-2 in Marion County near LM 17.25. This work will require a lane shift for the EB traffic, the WB traffic will be unaffected. Please slow down and use caution when driving through the work zone. [Talley Construction Company, Inc./Dunlap/CNZ244]
MARION COUNTY SR-283 [2.69-8.11] from 2.69 to 8.11 resurfacing with Cold In-Place Recycling (CIR): The contractor will be performing resurfacing operations on SR-283 from near SR-27 (LM 2.69) to the Sequatchie County line (LM 8.11). This work will require single lane closure controlled by flaggers. Please use caution when driving through the work zone.
[Road Worx, Inc./Dunlap/CNZ188]
POLK COUNTY SR-163 (BOWATER RD.) Utility Work both directions from LM .04 to LM .55: Flagger-assisted lane closures on SR-163 (Bowater RD) between Payne Rd and US411. Motorists should reduce speed and be prepared to stop. Trucks, arrow board/message boards, flaggers, and barrels/cones will be present 04/30/2026 through 05/06/2026 from 9 am to 2 pm [2025-781)
POLK COUNTY SR-314 [0-6.08] from SR-40 (US-64) to SR-33 (US-411) resurfacing: During this reporting period, the contractor will continue resurfacing work on SR-314. Temporary lane closures and flagging operations will occur while work is performed. At times, traffic will be reduced to one lane. Motorists should use caution and reduce speed when traveling through the work zone.
[Wright Brothers Construction Company, Inc./Cleveland/262011]
POLK COUNTY SR-68 over SR-40 the construction of bridges: During this reporting period, the contractor will continue construction on the SR-68 South bridge. All SR-68 traffic will use the newly constructed SR-68 North bridge while construction occurs on the new SR-68 South bridge. All SR-40/SR-68 interchange traffic will utilize the SR-68 North interchange ramps. A temporary 3-way stop has been implemented at the intersection of the SR-40 interchange ramp and SR-68. Motorists are encouraged to slow down when entering the construction zone and look out for new stop signs on SR-68 near the SR-40/SR-68 interchange.
[Wright Brothers Construction Company, Inc./Cleveland/CNZ042]
PUTNAM COUNTY I-40 TDOT Bridge Inspection both directions from MM 267.9 to MM 268.0: A routine inspection of the I-40 bridge over Indian Creek at Mile Marker 267.94 is scheduled for Tuesday, May 12. This inspection will result in lane closures on the bridge from 8 AM until 5 PM. The right eastbound lane and shoulder will be closed from 8 AM until 12 PM. The right westbound lane will be closed from 12 PM until 5 PM. Motorists are advised to approach the bridge with caution, be prepared to merge left, and be alert to the presence of inspection personnel and equipment on the bridge.
PUTNAM COUNTY I-40 TDOT Bridge Inspection both directions from MM 291.3 to MM 291.4: Routine Inspections of the I-40 bridges over Poplar Grove Road and the Falling Water River at Mile Marker 291.39 have been scheduled for May 13. Lane closures will be required on the bridge to allow the use of specialized access equipment. The right eastbound lane and shoulder will be closed on Wednesday, May 13 from 8 AM until 12 PM. The right westbound lane will be closed from 12 PM until 5 PM. Motorists are advised to approach the bridge with caution during these times, be prepared to merge left in advance of the bridge and be alert to the presence of workers and inspection equipment on the bridge.
PUTNAM COUNTY I-40 [303.6-304.2] from MM 303.6 to MM 304.2 bridge repair and resurfacing: Construction continues within the median of I-40. Traffic has been shifted along the project route. Motorists should use caution in the area and be aware of construction vehicles entering and exiting from the work zone. [Rogers Group, Inc./Crossville/CNZ290]
PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor will continue normal working activities throughout the project limits. During this work, temporary lane closures are possible, and flaggers will be present. Pigeon Roost Creek Road is closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. Motorists are encouraged to use caution while traveling through the work zone and should be aware of construction equipment adjacent to the roadway. [Rogers Group, Inc./Cookeville/CNV284]
PUTNAM COUNTY SR-136 [2.27-4.15] from I-40 Eastbound Ramps to SR-24 resurfacing: The contractor is scheduled to begin concrete curb work starting 05/10/26. During this work, the contractor will have one lane closed in each direction. Motorists should be prepared to stop as they approach the work zone, and they should be aware of construction equipment adjacent to the roadway. [Vulcan Construction Materials, LLC/Cookeville/CNZ293]
PUTNAM COUNTY SR-24 (CROSSVILLE HWY.) Utility Work both directions from LM 35.55 to LM 38.09: Eastbound and Westbound Lane closures on SR-24 (Crossville Hwy.) between E. Wilder Ave. and Walker Farm Rd. Motorists should reduce speed and be prepared to stop. Arrow board/message boards, flaggers, and barrels/cones will be present, 11/06/25 through 05/06/2026 from 9 am - 2 pm. [2025-521]
REGION 2 Interstate and state route thermoplastic marking re-tracing: The contractor will be onsite in Hamilton County on I-24 (LM 8.150 - 12.100), SR-17 (LM 2.540 - 3.650). SR-321 9LM 5.273 - 5.550), Bradley County SR311 at I-75 (LM 0.00 - 0.078), and in Polk County SR-40 (LM 9.880 - 16.901). During this work, the contractor will be performing a mobile operation as the crews retrace thermoplastic pavement lines. Motorists should use caution if they encounter the crew and stay of the edge lines as the material may be wet. [Mullen's Markings, Inc/Cookeville/262003]
REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short-term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. The contractor will have daytime outside shoulder closures on Bradley I-75 between MM 25 and MM 33.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
REGION 2 Region 2 snowplowable marker relense/replacement contract: The contractor is scheduled to begin re-lensing operations beginning 05/05/26 from the hours of 8 PM until 6 AM. The contractor will be working in Cannon and Warren Counties, and a mobile operation will be used with an attenuator truck shadowing the work convoy. Work will take place in Cannon County on SR-1, SR-53, SR-64, SR-96, SR-99, SR-145, SR-146, and SR-281. Work will also occur in Warren County on SR-1, SR-8, SR-30, SR-55, SR-56, SR-108, SR-127, SR-136, SR-286, SR-287, SR-288, SR-379, and SR-380. Motorists should use caution as they approach the work zones, and they should be prepared to stop as slow-moving vehicles or construction equipment is encountered.
[W.L. Markers Inc./Cookeville/262001]
REGION 2 the drain cleaning on various Interstate and State Routes: Drain cleaning operations are planned on I-75, SR-153 and I-24 in Hamilton County. These operations are mobile along the inside shoulders with impacts to adjacent traffic lanes and will occur at night between 8 PM and 6 AM. [Sweeping Corporation of America, Inc./Chattanooga West/CNZ286]
REGION 2 The on-call cable barrier repair on various Interstate and State Routes.: The contractor will have short-term shoulder and/or lane closures in order to perform cable barrier rail repair. These closures will take place daily Monday through Friday, during daylight hours on the interstates and some major divided highway state routes. There may also be nightly Sunday through Thursday from 7 PM to 6 AM, rarely and only as needed. At least one travel lane will remain open to traffic at all times. Typically, only a shoulder closure will be used in the median, but lane closures will be employed as needed. [LU, Inc./McMinnville/CNZ205]
REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor will have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.
[Reynolds Fence and Guardrail, Inc./McMinnville/CNZ112]
REGION 2 The random on-call asphalt pothole patching on various Interstate and State Routes: The contractor will be working in the following locations during this reporting period. Please be cautious of equipment entering and leaving the work zone. The contractor will be working Mondays - Fridays between 8 AM and 6 PM, Franklin County - SR50 between LM 14.5 and LM 24.5, Marion County - SR28 between LM 2.5 and LM 11.5
[Pavement Restorations, Inc./Chattanooga East/CNZ279]
REGION 2 the sweeping on various Interstate and State Routes: Sweeping operations are planned throughout Region 2 this reporting period. Sweeping operations are mobile operations along the inside and outside shoulders with impacts to adjacent traffic lanes. These operations will occur at night between 8 PM and 6 AM for interstates and high traffic state routes, while daytime sweeping can be anticipated between 9 AM to 3 PM for lower traffic state routes.
[Spears-Hopkins Paving Co., LLC/Chattanooga West/CNZ248]
VANBUREN COUNTY SR-111 [14.87-19.54] from Sparta Street to White County Line microsurfacing: The contractor will have occasional lane closures during daylight hours from 6 AM to 7 PM for microsurfacing-related operations. Additionally, lane closures on this multi-lane highway will occasionally carry through nighttime hours (24-hour lane closures) with proper signage for curing of concrete and other bridge-related setup as needed on infrequent occasions.
[Asphalt Paving Systems, Inc./McMinnville/CNZ177]
WHITE COUNTY SR-1 [0-7.7] from Van Buren County Line to SR-111 resurfacing: The contractor will be continuing resurfacing operations. During this work, one lane will be closed in each direction and workers will be present on the roadway. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop as they may encounter slow-moving traffic. [Asphalt Paving Systems, Inc./Cookeville/262014]
WHITE COUNTY SR-111 [15.25-16.25] from O'Connor Rd to Old Kentucky Rd culvert replacement: The contractor will be continuing work on installation of a box culvert. During this work, traffic will remain in one lane, and two-way traffic will be running on the northbound section of SR-111. Motorists are encouraged to use caution as they approach the work zone, and they should be prepared to stop. Motorists should also be aware of the speed limit reduction in place and follow all signs displayed. [Rogers Group, Inc./Cookeville/CNZ902]
RESTRICTIONS
CAMPBELL, COFFEE, DAVIDSON, DICKSON, GILES, GREENE, HAYWOOD, KNOX, MCMINN, SHELBY, AND WILLIAMSON COUNTY - CNX913:
CUMBERLAND COUNTY - CNZ206: Both lanes of SR-24 are closed at LM 15.06 to LM 15.6.
###