Navigating campus during summer construction

A number of projects will cause disruption to areas of campus throughout the summer.

Albertsons Library

The library will be closed twice for a switchgear replacement.

  • May 11-29: Full building outage - no access
  • June 29 to July 16: Partial outage - the building will be open during this time, but there will be no A/C available in the building

Math Building

The Math Building will be closed for a switchgear replacement.

  • June 1-29: Full building outage - no access

West Stadium Lot and Bronco Lane

Work in this area will begin May 11 and continue through Sept. 11. There are four phases of the project and a different are will be closed during each phase. Sections of the road and parking lot will reopen upon the completion of each phase.

  • Phase 1: West section of Bronco Lane
  • Phase 2: North section of West Stadium lot between ExtraMile Arena and Chaffee Hall. This phase also includes a small portion of the lot in front of the entrance to the North TowerStueckle Sky Center
  • Phase 3: Southwest section of West Stadium lot between Bronco Gym and ExtraMile Arena
  • Phase 4: East section of Bronco Lane and a small section of the West Stadium lot in front of the entrance to the Stueckle Sky Center
Boise State University published this content on May 04, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on May 04, 2026 at 21:00 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]