Weekly Traffic Impact Report Week of November 3, 2026

9th Street Corridor Improvements

Project Status

Expected to be completed by April 2027.

Traffic Impacts

Lane closure, expect delays between 7:00 a.m. to 5:00 p.m. Monday through Friday

  • 9th Street from North Carpenter Road to L Street

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Intersection of South Carpenter Road and West Hatch Road

Project Status

Expected to be completed by the end of November 2026.

Traffic Impacts

Traffic control will be in place from 7:00 a.m. to 5:00 p.m.

  • Intersection of South Carpenter Road and West Hatch Road into Riverdale Avenue
  • All turn-pockets off West Hatch Road entering the subdivision will be closed.
  • Detour in place that routes vehicles southbound to West Whitmore Avenue and back around to Vivian Road to enter from the far west side of the subdivision.

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Woodland Lift Station

Project Status

Expected to be completed by the end of July 2027.

Traffic Impacts

Periodic traffic control with lane shift and closures.

  • on the corner of Woodland Avenue and Poust Road

Motorists are advised to slow down, use caution, and take alternate routes when possible.

North County Corridor

Traffic Impacts

  • Roselle Avenue opened, one lane each direction between Claribel Road and Plainview Road, 25 mph.
  • Terminal Avenue will be closed to through traffic between Townsend Avenue to Plainview Road
  • Claribel Road will be closed between Roselle Avenue and Claus Road

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Codoni Lift Station

Project Status

Expected to be completed by the end of February 2027.

Traffic Impacts

Periodic traffic control with lane shift and closures.

  • Codoni Avenue between Leckron Road and Finch Road

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Claus Road & Merle Avenue Roundabout

Project Status

Expected to be completed by February 2027.

Traffic Impacts

  • Merle Avenue between Claus Road and Thomas Court will be closed to through traffic during construction.
  • Residents within the closure area will continue to have access to and from their homes.

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Highway 99 Water Main Crossing Improvements I Street, G Street, and Sierra Drive

Project Status

Expected to be completed by March 2027.

Traffic Impacts

  • The Westbound Number 2 lane on I Street will be closed between 5th Street and 6th Street at Highway 99 overpass.

Motorists are advised to slow down, use caution, and take alternate routes when possible.

Oakdale Road near Mable Avenue

Project Status

Dates: Thursday, November 5, 2026, and Friday, November 6, 2026

Traffic Impacts

Temporary lane closures and traffic shifts.

  • Temporary North Bound Lane Closures - Oakdale Road near Mable Avenue

Traffic will remain open in both directions through the work area. Drivers should expect reduced lane availability, shifted travel lanes, and possible delays.
Please allow extra travel time, slow down, and follow posted signs and traffic control devices. Use caution around workers and equipment.

City of Modesto, CA published this content on November 03, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on November 03, 2026 at 23:43 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]