Tyler to improve neighborhood streets through 2026 Asphalt Enhancement Project

The streets people use every day close to home are the focus of the 2026 Asphalt Enhancement Project.

This year's work will target about 20 miles of neighborhood streets across Tyler, refreshing worn pavement and creating a smoother ride. Crews will remove the top layer of asphalt and replace it with a new surface, helping extend the life of each roadway and reduce the need for more costly repairs later.

The City Council approved a $3,728,915.15 contract with Reynolds and Kay for the Asphalt Enhancement Project. Construction is expected to begin as early as April 2026 and continue through November 2026, weather permitting.

The project will include improvements to the following streets:

Sunnybrook Area

  • Sunnybrook Drive from South Vine Avenue/U.S. Highway 155 to Old Jacksonville Highway
  • Sunnybrook Drive from Old Jacksonville Highway to Green Lane
  • Crockett Drive from San Jacinto Street to Robertson Avenue
  • Terre Haute Drive from Vine Avenue to Robertson Avenue
  • Aurora Drive from Buena Vista Street to Terre Haute Drive
  • Oak Lane from Sunnybrook Drive to West Ellis Street
  • North Azalea Drive from West Azalea Drive to Sunnybrook Drive
  • West Azalea Drive from North Azalea Drive to South Azalea Drive
  • West Camellia Street from West Azalea Drive to Sunnybrook Drive
  • South Azalea Drive from West Azalea Drive to Dogwood Drive
  • Graham Drive from West Azalea Drive to Robertson Avenue
  • Brookside Drive from Beechwood Drive to Woodlark Drive
  • Zelwood Drive from Brookside Drive to dead end
  • Woodland Hills Drive from Old Jacksonville Highway to Cloverdale Drive
  • Robertson Avenue from Crockett Drive to Old Jacksonville Highway

Wall Area

  • Donnybrook Avenue from Houston Street to 5th Street
  • East Lake Street from Broadway Avenue to Donnybrook Avenue
  • Fannin Avenue from Dobbs Street to 1st Street
  • 1st Street from Wall Avenue to Highland Avenue
  • Wall Avenue from East Lake Street to 5th Street
  • Wall Avenue from 5th Street to 8th Street
  • Henderson Avenue in the Wall Avenue area
  • 6th Street from Donnybrook Avenue to Highland Avenue
  • Guinn Drive from west segment to South Fleishel Avenue
  • Knob Hill Drive from dead end to Guinn Drive
  • Guinn Drive from South Fleishel Avenue to east segment
  • 6th Street from South Fleishel Avenue to Magnolia Street

Owens Area

  • Owens Avenue from Martin Luther King Jr. Boulevard to Nutbush Street
  • Owens Avenue from Vance Street to Hillsboro Street
  • Carlyle Avenue from Martin Luther King Jr. Boulevard to East Vance Street

Alice Area

  • Rogers Street from Horn Avenue to Lex Avenue
  • Lex Avenue from Story Street to Duncan Street
  • Lyndon Avenue from Duncan Street to Alice Street
  • Alice Street from Angeline Avenue to Lyndon Avenue

Pleasant Area

  • Glenbrook Drive from Marilyn Drive to Boldt Drive
  • Pleasant Drive from Glenbrook Drive to Boldt Drive
  • Montrose Drive in the Sterling Drive area
  • Castle Drive from McDonald Road to Barbara Street

In addition to street improvements, the project includes alley paving repairs funded by the Streets Department, as well as pavement and striping improvements to City-owned parking lots funded by the Facilities Services Department.

Funding for the project includes $3,433,566.55 from the Half Cent Sales Tax Fund, $161,130 from the Streets Department Fund, and $134,218.60 from the Facilities Fund.

City of Tyler, TX published this content on April 08, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 08, 2026 at 19:11 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]