What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the I-285/I-20 East Interchange project. The project will reconstruct the interstate system-to-system ramps at the I-285/I-20 East Interchange and add a combination of collector-distributor (CD), or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange.
Where/When: Traffic impacts on the I-285/I-20 Interchange project from Friday, March 13, 2026, through Friday, March 20, 2026.
DAYTIME CLOSURES:
Friday, March 13, through Friday, March 20, from 9 a.m. to 2 p.m.
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound: Single, right- or left- lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: Single, right- or left-lane and shoulder closure from Panola Road (MM 71.4) to Fairington Road (MM 72.8)
Friday, March 13, through Friday, March 20, from9 a.m. to 4 p.m.
-
Hillandale Drive at DeKalb Medical Parkway
Flagging Operation
Friday, March 13, through Friday, March 20, from 9 a.m. to 4 p.m.
Flagging Operation
Friday, March 13, through Friday, March 20, from 9 a.m. to 4 p.m.
-
Chupp Way at Fairington Road
Flagging Operation
OVERNIGHT CLOSURES AND TRAFFIC PACING:
Friday, March 13, through Friday, March 20, from 7 p.m. to 5 a.m.
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Wesley Chapel Road (MM 69.5) to Panola Road (MM 71.3)
-
I-20 Eastbound (connecting lanes or CD lanes): Single to double, right- or left-lane and shoulder closure from I-285 Interchange (MM 67.3) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound: Single to double, right- or left-lane and shoulder closure from Columbia Drive (MM 66.8) to Wesley Chapel Road (MM 69.5)
-
I-20 Eastbound to I-285 Northbound single to double right or left lane, left-and right lane closure
-
I-20 Eastbound: single right lane closure on Wesley Chapel off ramp
-
I-20 Eastbound: Single to double, right or left-lane closure from Panola Road (MM 71.3)to Fairington Road Overpass
Friday, March 13, through Friday, March 20, from 8p.m. to 5 a.m.
-
I-285 Southbound: single to double left or right lane closure from Interchange to Columbia Drive
-
I-285 Southbound: single to double right lane and shoulder closures from Glenwood to Interchange
-
I-285 Northbound: Single to double left, or right lanes and shoulder closure from Columbia to Interchange
-
I-285 Northbound: Single to double left, or right lanes and shoulder closure from Interchange to Glenwood
Friday, March 13, through Friday, March 20, from 9 p.m. to 5 a.m.
-
I-20 Westbound: Single to double, left-lane closure from Wesley Chapel Road (MM 69.5) to Columbia Drive (MM 66.8)
-
I-20 Westbound: Alternating, single, left- and right-lane and shoulder closure from Panola Road (MM 71.4) to Wesley Chapel Road (MM 68.5)
-
I-20 Westbound: Single to double, right or left-lane closure from Fairington Road Overpass to Panola Road (MM 71.3)
Wednesday, March 18, through Friday, March 20, from 9 p.m. to 5 a.m.
-
I-20 Eastbound from the Snapfinger Creek bridge to the Fairington Rd overpass - Traffic Shift
|
|
Activity
|
Start Date
|
End Date
|
Times
|
|
I-20 Westbound
|
-
I-20 from Panola Road to Wesley Chapel Road
|
Single to double right or left lane and shoulder closures
|
March 13
|
March 20
|
9 p.m. - 5 a.m.
|
-
I-20 from Wesley Chapel to Columbia Drive
|
Single to double, left-lane closure
|
March 13
|
March 20
|
9 p.m. - 5 a.m.
|
-
I-20 Westbound closure from Fairington Road Overpass to Panola Road (MM 71.3)
|
Single to double, right or left-lane
|
March 13
|
March 20
|
9 p.m. - 5 a.m.
|
|
I-20 Eastbound
|
-
I-20 from Wesley Chapel Road to the Panola Road
|
Single, right-lane and shoulder closure
|
March 13
|
March 20
|
9 a.m. - 2 p.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single, right-lane and shoulder closure
|
March 13
|
March 20
|
9 a.m. - 2 p.m.
|
-
I-20 from Columbia Drive to Wesley Chapel
|
Single, right- or left-lane and closure
|
March 13
|
March 20
|
9 a.m. - 2 p.m.
|
-
I-20 from Wesley Chapel Road to Panola Road
|
Single to double, right-or left-lane and shoulder closure
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
-
I-20 connecting (CD) lanes from the I-285 Interchange to Wesley Chapel Road
|
Single to double, right- or left-lane and shoulder closure
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
-
I-20 Columbia Drive to Wesley Chapel Road
|
Single to double, right- and left-lane and shoulder closure
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
-
I-20 From Wesley Chapel Road to Panola Road
|
Traffic shift in all eastbound lanes
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
-
I-20 Eastbound to I-285 Northbound
|
single to double right or left lane, left-and right lane closures from
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
-
I-20 Eastbound closure on Wesley Chapel off ramp
|
Single right lane closure
|
March 13
|
March 20
|
8 p.m. - 5 a.m.
|
-
I-20 Eastbound closure from Panola Road (MM 71.3)to Fairington Road Overpass
|
Single to double, right or left-lane
|
March 13
|
March 20
|
7 p.m. - 5 a.m.
|
I-285 Southbound
|
|
|
|
|
-
I-285 Southbound from Interchange to Columbia Drive
|
Single to double left or right lane closure
|
March 13
|
March 20
|
8 p.m. - 5 a.m.
|
-
From Glenwood Road to the I-20 Interchange
|
Single to Double, and right-lane and shoulder closures
|
March 13
|
March 20
|
8 p.m. - 5 a.m.
|
|
I-285 Northbound
|
|
|
|
|
-
From Columbia Drive to the I-20 Interchange
|
Single to double left, or right lanes and shoulder closure
|
March 13
|
March 20
|
8 p.m. - 5 a.m.
|
-
From Interchange to Glenwood
|
Single to double left, or right lanes and shoulder closure
|
March 13
|
March 20
|
8 a.m. - 6 p.m.
|
|
Flagging Operation
|
|
|
|
|
|
Miller Road over I-20
|
Flagging Operation
|
March 13
|
March 20
|
9 a.m. - 4 p.m.
|
Hillandale Drive at DeKalb Medical Parkway
|
Flagging Operation
|
March 13
|
March 20
|
9 a.m. - 4 p.m.
|
|
Chupp Rd
|
Flagging Operation
|
March 13
|
March 20
|
9 a.m. - 4 p.m.
|
|
|