Update on electricity infrastructure incident and stabilization measures.

The Nelson Mandela Bay Municipality wishes to update residents on the ongoing restoration work on the Chelsea-Arlington-Walmer-Summerstrand line. Out of the nine damaged structures, seven have been safely dismantled, and twenty foundation holes for the new poles and stays have been completed in preparation for the replacement structures.

Additional earth-moving equipment will be brought to site to speed up excavation, bush clearance, and the construction of access roads in preparation for conductor stringing. Five new structures have already been delivered to the site, with an additional five monopoles expected today, along with the first batch of reconstruction materials. An extra team will also arrive tomorrow (Sunday) to help expedite the work.

We sincerely apologise for the inconvenience caused by this incident and thank all residents and businesses for their patience and understanding during this time.
Nelson Mandela Bay Municipality published this content on March 21, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on March 21, 2026 at 12:38 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]