City of Verona, WI

10/24/2025 | Press release | Distributed by Public on 10/24/2025 09:05

Road Construction Update

Please be aware of the following closures and construction activities:

Paoli St. & Valley Rd. (SSM Clinic Area)

  • Westbound on-ramp to US 18/151 closed Oct. 24 at 8 PM - Oct. 27 at 6 AM
    Crews will install utility pipes and new concrete pavement overnight Friday and early Saturday.
  • Valley Rd remains closed through late November.
    Rock Blasting scheduled Oct. 30 - Nov. 7 for utility trench work.

  • Southbound Paoli St. is scheduled to reopen Nov. 3, with access to the westbound US 18/151 on-ramp.

  • HWY 69 northbound and southbound traffic remains open south of the westbound US 18/151 ramps.

  • Eastbound off-ramp from US 18/151 scheduled to be closed Nov. 14 - 17 (coordinated with a WisDOT project).

Shady Oak Ln (MMSD Project)

  • Shady Oak Lane remains closed to through traffic and is expected to reopen by early November

Mark Dr Reconstruction (City of Verona)

  • Utility installation nearly complete, started street grading, concrete curb and gutter pour next week
  • Pavement will be installed and streets reopened by Thanksgiving, construction will then be paused for Winter.

W Verona Ave and Legion St (City of Verona)

  • Paved and reopened to traffic
  • New poles and traffic signal installation expected by mid-November

Edward St Resurfacing - Westridge Pkwy to Thompson St (City of Verona)

  • Open for local traffic on gravel base
  • Concrete work to be completed next week
  • Expected project completion by mid-November
City of Verona, WI published this content on October 24, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 24, 2025 at 15:05 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]