San Francisco - Caltrans will complete the northbound parking inlet section of the 19th Avenue Rehabilitation Project on Monday, December 15th which began Monday, December 1, 2025, at Sloat Boulevard, moving north toward Lincoln Way. On Monday, December 15, Caltrans begins the southbound parking inlet section of the project at Lincoln Way, moving south toward Sloat Boulevard. These two sections of the project are part of a broader project to rehabilitate 19th Avenue (State Route 1).
Project Details
The project will repave all three lanes in each direction of State Route 1 (19th Avenue) between Lincoln Way and Holloway Avenue, approximately 18.8 lane miles, and Park Presidio Boulevard and California Street intersection.
Traffic Impacts
Phase 1 Traffic Impacts:
Lane Reductions: Throughout phase 1, two lanes always open and one lane closed in the direction of active work. All lanes will be open in the opposite direction.
Phase 2 Traffic Impacts:
Lane Reductions: Throughout phase 2, one lane will be open, and two lanes closed in the direction of active work. All lanes will be open in the opposite direction.
For real-time traffic information, visit: quickmap.dot.ca.gov
Caltrans thanks the traveling public for their patience while this important work is completed.
Please visit Caltrans https://www.sfhighwayprojects.com.
For 24/7 traffic updates, please visit 511.org: https://x.com/511SFBay
For real-time information, visit Caltrans QuickMap: https://quickmap.dot.ca.gov
Follow us on X: https://x.com/CaltransD4
Or call 1-800-472-7623, 1-800-427-ROAD for state highway conditions statewide.