MoDOT TRAFFIC ALERT: Webster County Route A CLOSED just North of Normandy Road…

Where: Webster County Route A CLOSED just North of Normandy Road in Diggins

When: Monday, November 10, until Thursday, November 20

What: Contractor crews will connect Route A to the new North Outer Road as part of the U.S. Route 60 and Webster County Route A Interchange improvements project between Diggins and Fordland. When the work on Route A is complete and the route is reopened, traffic will be detoured to Route O using the new North Outer Road to connect with U.S. Route 60.

Traffic Impacts:

  • Webster County Route A CLOSED just North of Normandy Road in Diggins
  • U.S. Route 60 lane Closures between Webster County Route A and Route O in Diggins
    • Eastbound Route 60 passing lane Closed
    • Westbound Route 60 driving lane Closed
  • U.S. Route 60 Open
  • Drivers urged to find alternate routes
  • No signed detours planned
  • Signs and message boards will alert drivers approaching the work zone
  • Check MoDOT's Traveler Information Map for road closures/traffic impacts

Weather and/or construction delays could alter the work schedule.

To get project updates or sign up for project emails, visit: https://www.modot.org/projects/us-route-60-route-and-route-z-interchange-improvements-webster.

Project Summary:

  • Build interchange at U.S. Route 60 and Webster County Route A
  • Build bridge over Route 60 and BNSF Railroad
  • Connect Route NN to new Route A interchange with north Outer Road
  • Roundabout at new Route NN/Route A intersection south of Route 60
  • Construct south Outer Road between Route Z in Fordland and Route A in Diggins along the south side of BNSF Railroad
  • Remove nine railroad crossings: Route NN, Greenbriar Drive, Honor Camp Lane, Tandy Road, Hummingbird Lane, Bluebird Lane, three additional private drives
  • Remove nine Route 60 highway intersections/private access: A, NN, Route O (right-in, right-out only), as well as Bluebird Lane, Hummingbird Lane (south side), Honor Camp Lane (south side), Greenbriar Drive, and two private accesses

Contractor: Capital Paving & Construction LLC, Jefferson City

The awarded construction cost is $39.8 million.

The project is scheduled for completion in December 2027.

END

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

Follow MoDOT's Southwest District: Facebook | X | Instagram|YouTube

Take the Challenge! Buckle Up/Phone Down

State of Missouri published this content on October 30, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 30, 2025 at 17:18 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]