This notice revises the Federal Energy Regulatory Commission's (Commission) schedule for processing White Pine Waterpower, LLC's (White Pine) license application for the White Pine Pumped Storage Project. A prior notice issued on March 3, 2025, identified an anticipated schedule for issuance of draft and final National Environmental Policy Act (NEPA) documents and a final order for the project. After the issuance of that notice, White Pine requested an extension of time to complete its hydrogeologic study with a final study report to be filed by January 31, 2027. Commission staff issued a letter approving the extension of time on March 10, 2026. To account for the additional time needed for White Pine to complete the study and file the study report, the application will be processed according to the following revised schedule.
Notice of Ready for Environmental Analysis: April 2027.
Draft NEPA Document: January 2028.
Final NEPA Document: July 21, 2028.
The project is covered under Title 41 of the Fixing America's Surface Transportation Act (FAST-41). Under FAST-41, agencies are to publish completion dates for all federal environmental reviews and authorizations. This notice identifies the Commission's anticipated schedule for issuance of the final order for the project, which is based on the revised issuance date for the final NEPA document. We currently anticipate issuing the final order for the project no later than:
Issuance of Final Order-October 19, 2028
If a schedule change becomes necessary, additional notice will be provided so that interested parties and government agencies are kept informed of the project's progress.
(Authority: 18 CFR 2.1)