Illinois Department of Transportation

08/31/2026 | Press release | Distributed by Public on 08/31/2026 08:40

Rebuilding Will County: Construction season brings another round of major improvements to region

CHICAGO - Rebuild Illinois is continuing to improve mobility, safety and quality of life in Will County, with the Illinois Department of Transportation delivering multiple major projects this construction season. Made possible by Gov. JB Pritzker's historic capital program, nine projects combined represent a total investment of more than $91.8 million, creating and maintaining good-paying jobs throughout the region. ​ ​

"The historic Rebuild Illinois program continues to transform our infrastructure and enhance key economic corridors across the state," said Gov. Pritzker. "Our ambitious capital program is putting Illinoisans to work as we improve regional transportation systems, encourage new economic activity and build a better future for all of Illinois." ​ ​

Of the nine major projects in Will County, three are scheduled to be completed in 2026, with the remaining six projects completed between 2027 and 2030.

  • U.S. 6 (Scott Street) from Washington Street to Ruby Street resurfacing and ADA improvements. Work began in 2024 and anticipated to be completed this fall. Daily lane closures are in place.
  • U.S. 30 (Cass Street) at the Des Plaines River bridge superstructure replacement. Work began in 2025 and is anticipated to be completed in 2027. A full closure is in place during construction.
  • U.S. 30 (Lincoln Highway) from Center Street to Collins Street and Center Street from U.S. 30 to Jefferson Street resurfacing. Work began in 2024 and anticipated to be completed this fall. Daily lane closures are in place.
  • Interstate 57 at Pauling Road overpass new bridge deck, shoulder repair, retaining wall, culvert extension and culvert repair. Work began in 2025 and is expected to be completed later this fall. A detour using Illinois 50, Monee Manhattan Road and South Harlem Avenue are in place.
  • Illinois 171 (Collins Street) from Cass Street to Division Street resurfacing. Work is anticipated to begin this fall and be completed in 2027. Daily lane closures will be in place.
  • U.S. 45 from Colorado Avenue to Old Frankfort Way resurfacing. Work is anticipated to begin this fall and be completed in 2027. Daily lane closures will be in place.
  • U.S. 30 (Jefferson Street) at the Des Plaines River new bridge deck and bridge repairs. Work is anticipated to begin in 2028 and be completed in 2030. A detour will be in place.
  • Illinois 53 (Chicago Street) from U.S. 52 (Doris Avenue) to West Manhattan Road resurfacing.Work is anticipated to begin in spring 2029 and be completed in fall 2029.Daily lane closures will be in place.
  • Jackson Street at the Des Plaines River bridge superstructure rehabilitation. Work is anticipated to begin in 2027 and be completed in 2030. A detour will be in place.

"IDOT's investment in local infrastructure is a much-needed step toward repairing the roads that carry our communities and our economy every day," said state Sen. Rachel Ventura (D-Joliet). "Heavy truck traffic has taken a toll on many of these routes, leaving rough, deteriorated surfaces that affect everyone who travels them. Investing in resurfacing and strengthening these truck routes will not only extend the life of our roads, but also provide a smoother, safer ride for motorists and improve the movement of freight throughout our communities."

"This is a fantastic opportunity and a major win for Will County residents," said Assistant House Majority Leader Dee Avelar (D-Romeoville). "The Rebuild Illinois capital program will upgrade essential roadways, create jobs and drive local economic growth. As construction begins, let's remind ourselves to obey speed limits and drive carefully to protect road crews and keep projects on schedule."

"Rebuild Illinois continues to deliver results for Will County and the entire region," said Will County Executive Jennifer Bertino-Tarrant. "These improvements will strengthen access for residents and support our rapid pace of economic development. I appreciate Gov. Pritzker and IDOT for investing in our communities."

Passed in 2019, Rebuild Illinois is investing a total of $33.2 billion over six years into the state's aging transportation system, creating jobs and promoting economic growth. Rebuild Illinois is not only the largest capital program in state history, but also the first that touches all modes of transportation: roads and bridges, transit, waterways, freight and passenger rail, aviation, and bicycle and pedestrian accommodations. ​ ​ ​

"Thanks to Gov. Pritzker's Rebuild Illinois, we are continuing to deliver transformational projects up and down the state," said Illinois Transportation Secretary Gia Biagi. "We look forward to another safe construction season that benefits the region for decades to come." ​

Accomplishments through Year Seven of Rebuild Illinois include $25.6 billion of improvements statewide on 24,498 miles of highways, 959 bridges and 1,475 additional safety improvements. Visit https://idot.click/Rebuild-Illinois for information and highlights of other Rebuild Illinois projects happening throughout the state. ​

Will County 2026 RBI map.pdf

# # # ​

Illinois Department of Transportation published this content on August 31, 2026, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 31, 2026 at 14:40 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]