W. Club Boulevard Corridor Utility Rehabilitation Project Two-Week Look Ahead
July 18, 2025
The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at: www.durhamnc.gov/3705.
The contractor will be working Saturday, July 19. The contractor will be working from 7 a.m. to 5:30 p.m. installing water main on 9th Street, and sewer services on West Club Boulevard.
July 21-25, 2025
Crew 1 - Work continues on W. Club Boulevard between Alabama Avenue and Oval Drive with installation of 4" PVC sewer laterals and cleanouts. On Thursday and Friday the contractor will begin setting the asphalt base. This section of roadway is closed to through traffic.
Crew 2 - Work continues on Ninth Street between Safeway and W. Knox streets with installation of 12" water mains, valves, and fittings. There is an active temporary closure on Ninth Street between Safeway Street and W. Knox Street.
July 28-Aug 1, 2025
Crew 1 - Work continues on W. Club Boulevard between Alabama Avenue and Oval Drive and includes the contractor placing the asphalt base.
Crew 2 - Work continues on Ninth Street between Safeway and W. Knox streets with installation of 12" water mains, valves, and fittings. On Wednesday of this week the contractor will begin pressure testing the waterline and taking water samples. There is an active temporary closure on Ninth Street between Safeway Street and W. Knox Street.
Road closure information
An active temporary road closure remains in place on W. Club Boulevard between Alabama Avenue and Oval Drive.
Project contacts:
Wade Tong, Construction Team Manager, City of Durham, [email protected]
Zeke Urias, Project Manager, Moffat Pipe Inc., [email protected]