BART is performing rail destressing on the Yellow Line in Contra Costa County. To create a safe work space for our crews, BART will reduce service from two tracks to one while the work is taking place. The work is scheduled to start at midnight and continue until BART service begins the next morning. Riders can anticipate delays of 20-30 minutes on work nights. The next location for this rail maintenance work is between Lafayette and Pleasant Hill stations September 29-October 1, 2026.
Dates scheduled for this project include:
*September 29-30
*October 1
*October 15-17
*October 19
*October 22-24
*October 26
*November 12-14
*November 16
*November 19-20
*November 23
*December 3-5
*December 7
*December 17-19
*December 21