City of Fort Lauderdale, FL

10/08/2025 | Press release | Distributed by Public on 10/08/2025 16:07

Sanitary Sewer Force Main Rehabilitation and Replacement Project

Construction Update: Wednesday, October 8, 2025

The City of Fort Lauderdale is working with Lanzo Construction Co. to make improvements to the City's sewer system along SE 10th Avenue between E. Broward Boulevard and SE 2nd Street in Beverly Heights. Crews will be using a process called cured-in-place pipe (CIPP) lining, which is a trenchless method to rehabilitate underground sewer lines and extend their longevity while minimizing excavation and disruption. The work includes:

  • Cured-in-place pipe lining of approximately 1,300 feet of sewer lines.
  • Restoring the roadway, sidewalks and landscaping as needed.

Construction will begin on Wednesday, October 15, 2025, and is expected to be completed by late December 2025. Work will take place Monday through Friday between 7 a.m. and 7 p.m. This schedule is subject to change based on inclement weather or other unforeseen circumstances.

Traffic Impacts:

  • SE 10th Avenue will be closed in both directions from E. Broward Boulevard to SE 2nd Street throughout construction. The intersection of SE 10th Avenue and SE 2nd Street will also be closed for construction.
  • Traffic will be detoured to E. Broward Boulevard, SE 2nd Street, SE 9th Avenue, and SE 11th Avenue.
  • Traffic control personnel will direct traffic as needed.
  • Please follow the posted signs and drive with caution in the area.

We sincerely appreciate your patience and understanding as we complete this important infrastructure improvement. Neighbors with questions or concerns may contact the project hotline listed below.

Project Hotline: 1-800-214-4095 ext. 718

Email: [email protected]

See flyer

Construction Update: Monday, August 18, 2025

The City of Fort Lauderdale is working with Lanzo Construction Co. to make improvements to the City's sewer system along SE 10th Avenue between SE 15th Street and SE 18th Court in Harbordale. Crews will be using a process called cured-in-place pipe (CIPP) lining, which is a trenchless method to rehabilitate underground sewer lines and extend their longevity while minimizing excavation and disruption. The work includes:

  • Cured-in-place pipe (CIPP) lining of approximately 1,300 feet of sewer lines
  • Restoring the roadway, sidewalks and landscaping as needed

Construction will begin on Monday, August 25, 2025, and is expected to be completed by late December 2025. Work will take place Monday through Friday between 7 a.m. and 7 p.m. This schedule is subject to change based on inclement weather or other unforeseen circumstances.

Traffic Impacts:

  • SE 10th Avenue will be closed in both directions from SE 15th Street to SE 16th Street, including the intersections of SE 15th Street and SE 16th Street, throughout construction. Traffic will be detoured to Miami Road, Cordova Road and SE 17th Street.
  • One lane in each direction of SE 10th Avenue between SE 17th Street and SE 18th Court will be closed throughout construction.
  • The right shoulder along southbound SE 10th Avenue between SE 16th Court and SE 17th Street will be closed throughout construction.
  • Traffic control personnel will direct traffic as needed.
  • Please follow the posted signs and drive with caution in the area.

We sincerely appreciate your patience and understanding as we complete this important infrastructure improvement. Neighbors with questions or concerns may contact the project hotline listed below.

Project Hotline: 1-800-214-4095 ext. 718

Email: [email protected]

See flyer

Construction Update: Wednesday, August 6, 2025

The 24-hour drilling operation that was scheduled for Friday, August 8 through Sunday, August 10 has been rescheduled to Friday, August 15 through Sunday, August 17.

See updated flyer for work in Rio Vista

See updated flyer for work in Beverly Heights

Notice of 24-hour Drilling Operation

Crews will be performing horizontal directional drilling (HDD) to install a new sewer main along SE 9th Avenue in Rio Vista and Beverly Heights starting Friday, August 15 and continuing through Sunday, August 17.

Due to the nature of HDD work, this operation must run continuously, 24 hours a day, until it is complete. We understand the noise and inconvenience this operation may cause and will work diligently to complete it as soon as possible. It is not expected to exceed three days, however, the schedule is subject to change based on inclement weather or other unforeseen circumstances.

Work will take place at the entry and exit points where the pipes are being installed. The work zone in Rio Vista is at the intersection of SE 9th Avenue and SE 6th Street. The work zone in Beverly Heights is at the intersection of SE 9th Avenue and SE 2nd Court. Please follow posted signs and drive with caution in both areas.

The following traffic impacts are in effect in Rio Vista through October 2025:

  • SE 9th Avenue is closed from SE 5th Court to SE 8th Street.
  • Individual coordination is ongoing with residents with driveways within the full road to maintain access and parking.
  • Detours are in effect along SE 5th Court, US 1 / S Federal Highway, SE 11th Avenue, and SE 8th Street.

The following traffic impacts are in effect in Beverly Heights through October 2025:

  • The intersection of SE 9th Avenue and SE 2nd Court is closed.
  • SE 9th Avenue is open to local traffic only between E. Las Olas Boulevard and SE 2nd Court and between SE 2nd Court and SE 2nd Street.
  • SE 2nd Court is open to local traffic only between SE 8th Avenue and SE 9th Avenue and between SE 9th Avenue and SE 10th Terrace.
  • Detours are in effect along SE 2nd Street, SE 8th Avenue, SE 10th Terrace, and E Las Olas Boulevard.

We sincerely appreciate the patience and understanding of our neighbors as we complete this important infrastructure improvement.

Neighbors with questions or concerns may contact the project hotline: Phone: 1-800-214-4095 ext. 718 Email: [email protected]

Construction Update: Friday, August 1, 2025

Notice of 24-hour Drilling Operation

Crews will be performing horizontal directional drilling (HDD) to install a new sewer main along SE 9th Avenue in Rio Vista and Beverly Heights starting Friday, August 8 and continuing through Sunday, August 10.

Due to the nature of HDD work, this operation must run continuously, 24 hours a day, until it is complete. We understand the noise and inconvenience this operation may cause and will work diligently to complete it as soon as possible. It is not expected to exceed three days, however, the schedule is subject to change based on inclement weather or other unforeseen circumstances.

Work will take place at the entry and exit points where the pipes are being installed. The work zone in Rio Vista is at the intersection of SE 9th Avenue and SE 6th Street. The work zone in Beverly Heights is at the intersection of SE 9th Avenue and SE 2nd Court. Please follow posted signs and drive with caution in both areas.

The following traffic impacts are in effect in Rio Vista through October 2025:

  • SE 9th Avenue is closed from SE 5th Court to SE 8th Street.
  • Individual coordination is ongoing with residents with driveways within the full road to maintain access and parking.
  • Detours are in effect along SE 5th Court, US 1 / S Federal Highway, SE 11th Avenue, and SE 8th Street.

The following traffic impacts are in effect in Beverly Heights through October 2025:

  • The intersection of SE 9th Avenue and SE 2nd Court is closed.
  • SE 9th Avenue is open to local traffic only between E. Las Olas Boulevard and SE 2nd Court and between SE 2nd Court and SE 2nd Street.
  • SE 2nd Court is open to local traffic only between SE 8th Avenue and SE 9th Avenue and between SE 9th Avenue and SE 10th Terrace.
  • Detours are in effect along SE 2nd Street, SE 8th Avenue, SE 10th Terrace, and E Las Olas Boulevard.

We sincerely appreciate the patience and understanding of our neighbors as we complete this important infrastructure improvement.

Neighbors with questions or concerns may contact the project hotline: Phone: 1-800-214-4095 ext. 718 Email: [email protected]

See flyer for work in Rio Vista

See flyer for work in Beverly Heights

UPDATE: July 17, 2025

Construction will begin in Rio Vista and Beverly Heights as part of the next phase of this project on Monday, July 21 through October 2025.

Traffic Impacts in Rio Vista:

  • Road closures along SE 9th Ave. from SE 5th Ct. to SE 6th Ct.
  • Residents with driveways within the full road closure will be allowed access with coordination.
  • Detours will be in effect along SE 5th Ct., S Federal Hwy., SE 11th Ave., and SE 6th Ct.
  • Drive with caution in the area, especially when construction workers and vehicles are present.
  • Please follow pedestrian crosswalk signage.

See flyer for work in Rio Vista

Traffic Impacts in Beverly Heights:

  • Road closure at the intersection of SE 9th Ave. and SE 2nd Ct.
  • Local traffic only along SE 9th Ave. and SE 2nd Ct.
  • Detours will be in effect along SE 2nd St., SE 8th Ave., SE 10th Ter., and E Las Olas Blvd.
  • Drive with caution in the area, especially when construction workers and vehicles are present.
  • Please follow pedestrian crosswalk signage.

See flyer for work in Beverly Heights

Neighbors with questions or concerns may contact the project hotline:

Phone: 1-800-214-4095 ext. 718 Email: [email protected]

UPDATE: July 10, 2025

Crews will be performing horizontal directional drilling (HDD) to install new a sewer main along Miami Road from SE 12th Street to SE 15th Street in Harbordale starting Friday, July 11, and continuing through Sunday, July 13.

Work will take place at the intersections of Miami Road and SE 12th Street and Miami Road and SE 15th Street. Those are the entry and exit points where the pipes are being installed.

Due to the nature of HDD work, this operation must run continuously, 24 hours a day, until it is complete. A noise ordinance exemption has been approved for this work and will not exceed three days.

The following traffic impacts are in effect in Harbordale as part of the current phase of construction:

  • Miami Road is open to local traffic only between SE 12th Street and SE 12th Court.
  • Miami Road is open to local traffic only between SE 14th Court and SE 15th Street.
  • Eastbound SE 12th Street is open to local traffic only between US 1 / S. Federal Highway and SE 9th Avenue.

These roads are expected to reopen in late July when restoration is completed. This schedule is subject to change based on inclement weather or other unforeseen circumstances.

Please follow posted signs and drive with caution in the area.

We understand that this is an inconvenience to the community, and we sincerely appreciate your patience and understanding as we complete this important infrastructure improvement.

Neighbors with questions or concerns may contact the project hotline:

Project Hotline: 1-800-214-4095 ext. 718 Email: [email protected]

UPDATE: May 18, 2025

The City of Fort Lauderdale and Lanzo Construction are launching a multi-phase infrastructure improvement project along the city's wastewater network.

Phase 1 of the project will soon begin in the Harbordale neighborhood.

These improvements are designed to enhance the reliability, capacity, and environmental safety of Fort Lauderdale's wastewater system.

Where: Construction will occur along southbound Miami Rd. and SE 10th Ave. and along SE 15th St. between Miami Rd. and SE 10th Ave, near Harbordale Elementary School.

When: Phase 1 construction will begin in June 2025 and is expected to be completed in August of 2025.

Traffic Impact:

  • Lane closures and detours will be in effect
  • Increased traffic congestion
  • Movement of construction vehicles
  • Pedestrian crosswalk impacts
  • Delays in public transit may occur

Alternative Parking: Alternative parking zones are available for residents on SE 15th St. during construction hours. Please refer to the image for designated Harbordale neighborhood parking areas.

Traffic Impacts:

  • Partial lane closures Southbound Miami Rd. and SE 10th Ave.
  • Full lane closure on SE 15th St. between Miami Rd. and SE 10th Ave.
  • Increased traffic congestion
  • Construction vehicle movement throughout the area
  • Pedestrian crosswalk safety precautions
  • Potential public transit delays

Contact Information:
Project Hotline: 1-800-214-4095 ext. 718
Email: [email protected]

Original Post: December 2, 2024

The City of Fort Lauderdale and Lanzo Construction Company are working to upgrade approximately 23,370 feet of large sanitary sewer pipelines along NE/SE 9th and 10th avenues, from Sunrise Boulevard to the George T. Lohmeyer Wastewater Treatment Plant. The project includes:

  • Rehabilitation of over 13,000 feet of existing sewer pipelines
  • Installation of over 10,000 feet of new sewer pipelines
  • Restoration of existing sewer connections
  • Road resurfacing as needed

Project Dates and Times

Construction will begin in December of 2024, and is expected to be completed by August of 2026. Work will take place Monday through Friday, from 8 a.m. and 5 p.m. This schedule is subject to change based on inclement weather or other unforeseen circumstances.

Traffic Impacts

  • Neighbors are asked to refrain from parking within the street daily between 8 a.m. and 5 p.m. until this project is completed
  • Access to driveways will be maintained unless work is taking place in the immediate area across from the driveway. Crews will attempt to coordinate with neighbors prior to the start of asphalt operations
  • Updates will be provided on any additional impacts to traffic or parking
  • Please follow posted signs and drive with caution in the area

Thank you for your patience as we strive to upgrade our wastewater system as quickly as possible.

For more information or questions, contact:

Kristin Jaggard, Project Manager II | 954-828-5663 or [email protected]

City of Fort Lauderdale Neighbor Service Center | 954-828-8000 or [email protected]

For PDF format, click here

City of Fort Lauderdale, FL published this content on October 08, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on October 08, 2025 at 22:07 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]