01/09/2025 | Press release | Distributed by Public on 01/09/2025 16:23
Anderson County
Palestine crews will be performing edge repairs throughout the county. Expect lane closures throughout the day.
Anderson County construction projects updates:
US 175 Widening Project
The contractor is scheduled to continue working on the new westbound bridge and setting beams on the new eastbound side. The contractor is also scheduled to install new pavement and road surface on the westbound side. FM 1892 has been reopened to the traveling public. Project consists of expansion to a four-lane roadway with new bridges across the Neches River.
US 79 Truck Parking Area
The contractor is awaiting final acceptance. No work is scheduled this week. The project includes concrete curb and gutter, earthwork, and drainage improvements.
Gus Engeling Texas Parks and Wildlife
The contractor is awaiting final acceptance. No work is being performed this week. The project includes surface treatment, pavement striping, and drainage improvements.
----------------------------------------
Cherokee County
This week, Jacksonville and Rusk crews will perform bridge maintenance at various locations throughout the county. Lane closures should be expected. Traffic will be controlled by flaggers.
Cherokee County construction projects updates:
SH 204
The contractor is scheduled to work on the culvert extensions and stormwater plan. Motorists should drive with caution. The project consists of adding a super-two highway section.
FM 2339 - SH 110
This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent retaining wall to address slope failure on SH 110. Work is currently suspended on this project, pending a redesign. No lane closures are anticipated. Motorists should drive with caution.
US 69 and FM 2493 Grade Separated Interchange Realignment - SH 110
FM 2493 - From 0.3 mi south of FM 344 to US 69 near Bullard
Construction of drainage structures and driveways is ongoing on FM 2493, east of US 69. No lane closures are expected. Motorists should drive with caution. This project consists of grade separated interchange and realignment of FM 2493, west of US 69.
US 175 Widening Project
The contractor is scheduled to work on the westbound roadway elements behind the traffic barrier. The east end of CR 3407 (Dip Rd) intersection is closed. Motorists are encouraged to use the west end of CR 3407 for access to US 175. Crews will be working on the bridge elements and setting beams. Crews will also continue clearing utility items and building storm drain systems. Motorists should use caution when traveling through the project. Large dirt-moving equipment will be entering and exiting US 175. The speed limit is reduced to 55 mph throughout the project limits. The project consists of expansion to a 4-lane roadway with new bridges, grading, asphalt, drainage structures, pavement markings, and signage.
US 69 Safety Improvement
The contractor has no work scheduled this week. The project consists of safety improvements consisting of the installation of a median cable barrier.
----------------------------------------
Gregg County
Gregg County construction projects updates:
SH 135 - Kilgore Traffic Circle
This project involves rebuilding the traffic circle and the entire width of the roadway up to the Rusk County line. Crews will demolish the west side of the road, which includes removing the old concrete, rebuilding the foundation, installing new concrete pavement, adding storm sewers, and completing lighting and striping. Two-way traffic is now open south of the traffic circle. The contractor is working on storm sewers and paving at the circle location.
FM 2206/Harrison Road Phase 1
This project will widen a two-lane road to four lanes with a center turn lane. The work includes adding drainage structures, a flexible base, curbs and gutters, sidewalks, asphalt paving, and pavement markings. Crews will be installing permanent striping and completing punch list items.
FM 2206/Harrison Road Phase 2
This project will widen a two-lane road to four lanes with a center turn lane. The work includes adding drainage structures, a flexible base, curbs and gutters, sidewalks, asphalt paving, and pavement markings. The contractor is working on punch list items.
High Street Bridge over UP Railroad
This project will replace the High Street bridge over the UP railroad. High Street is reduced to two lanes - one northbound and one southbound. Crews will build one half of the bridge at a time and are working on retaining walls and the new bridge structure. Drivers should expect delays.
SH 43
This project consists of milling approximately six inches off the surface and placing new hot mix. It also includes clearing the right of way, replacing driveway pipes, and striping. This week, the contractor will begin clearing the right of way.
----------------------------------------
Henderson County
This week, crews will be repairing base failures on FM 314. Expect lane closures with flaggers controlling traffic. Additional crews will be addressing erosion control and edge repair at various locations throughout the county. Crews will also perform sign maintenance and street sweeping.
Henderson County construction projects updates:
SH 198 Bridge Project
The contractor is awaiting final acceptance. No work is being performed this week. The work includes replacing bridges and approaches, grading, structures, base and surface work, retaining walls, curbs and gutters, fencing, and striping.
FM 316 Rehabilitation
The project is in time suspension and awaiting final acceptance. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
The contractor is awaiting final acceptance. No work is scheduled this week. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
Work is scheduled to resume the week of Jan. 13. This project includes sidewalk and pedestrian lane improvements.
SH 19 Super 2 Project
Work is scheduled to resume the week of Jan. 13. This project includes sidewalk and pedestrian lane improvements.
----------------------------------------
Rusk County
Henderson maintenance will be performing bridge maintenance at various locations throughout the county. Expect lane closures with flaggers controlling traffic. Crews are also scheduled to perform pothole repairs at various locations.
Rusk County construction projects updates:
US 84 - FM 225 East to CR 3155
This project consists of reconstructing US 84, extended structures, hot mix asphalt surface, new signs, and striping. Crews will be placing embankment at the cross culverts. Motorists should expect delays.
FM 3231 - Subgrade and Seal coat
This project consists of reconstructing FM 3231 completely. Work includes widening and re-laying subgrade, flex base material, and seal coat. Driveway culverts will be upgraded along with new signs and striping. The contractor is scheduled to install the metal beam guard fence. Expect lane closures with flaggers and a pilot car controlling traffic.
SH 315
This project consists of widening pavement edges and installing a four-foot space between the traffic lanes to separate opposing traffic for safety. Work will also include adding a passing lane in each direction of travel. The entire surface will be milled, and new hot mix will be placed for the final surface. Project also includes replacing some driveway pipes, metal beam guard fence, and striping. Contractor will be milling asphalt and laying new asphalt.
FM 2658
This project consists of reconstructing FM 2658 completely, from CR 344 to FM 1251. Work includes a new guard fence, treating subgrade, base material, seal coat, and striping. The contractor is scheduled to close the roadway at the south end of the project near the bridge. This is to accommodate the install of a new guardrail. Weather permitting, this closure is expected to last approximately three weeks. Property owners will still be allowed access to each end of the bridge. A detour has been established via FM 1251 to SH 43, then to FM 2658.
US 79 Rehabilitation
This project consists of rehabilitation of US 79 consisting of pavement repair, seal coat, asphalt surface, driveway culverts, and pavement markings. This week, the contractor is scheduled to place embankment on the slope. Motorists should expect delays with flaggers controlling traffic.
US 79 N
This project consists of repairing slope failure in the TxDOT right of way. The site will be excavated, and a new embankment will be placed. The contractor will be placing embankment on the slope if weather allows.
----------------------------------------
Smith County
Smith County crews will be repairing base failures on FM 15 at various locations. Expect lane closures with flaggers controlling traffic. A second crew will be on FM 3311 performing edge repairs. Expect lane closures with flaggers controlling traffic. There will also be a patch crew at various locations throughout the county.
Smith County construction projects updates:
Tyler State Park Bridge and Resurfacing Project
The contractor is pending repairs of final punch list items. This project consists of the construction of a new bridge and parking areas.
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
The contractor has no work scheduled this week. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
SH 31 Safety Improvement
The project consists of safety improvements consisting of the installation of a median cable barrier. No work is scheduled this week.
SL 323 Overlay on Existing Roadway
The contractor is scheduled to perform striping and check final punch list items. Lane closures are anticipated. This project consists of overlaying existing roadway with new asphalt.
I-20 Frontage Road at SH 155
The contractor has no work scheduled. No lane closures expected. Project consists of resurfacing the roadway, pavement markings, signage, and illumination.
Legacy Trails Extension
This project consists of a hike and bike trail development that includes construction of a 12-foot wide shared-use paths. No lane closures are expected this week.
FM 2493 Widen Non-Freeway
This project consists of widening the existing non-freeway roadway. Utility relocations are in progress, expect delays.
County Bridge Replacements
This project consists of replacing existing bridge facilities and approaches. Construction is on-going at CR 452 over Mill Creek. The bridge will be closed for the duration of construction.
SH 110 Preventative Maintenance
The project consists of preventative maintenance including planning, overlay, and pavement markings.
SH 110 Traffic Signals
This project consists of adding traffic signals to SH 110 and Loop 49 ramps and overlay operations.
I-20 Mill and Inlay at SH 135
The contractor is scheduled to perform permanent striping and punch list items. Lane closures are anticipated. Project consists of an overlay with a new surface, asphalt concrete pavement, planing, shoulder texturing, and pavement markings.
FM 16 Widening and Realignment
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A traffic shift is currently in place through town. Traffic will be in two lanes during this phase of construction. Crews will be hauling in embankment materials west of the high school. Crews will also work on tying in the proposed roadway into the newly constructed bridge. Crews will be removing the existing roadway and installing culverts in town. Motorists are urged to drive with caution and expect delays.
I-20 Mill and Inlay
The contractor has no work scheduled this week. Project consists of an overlay with new surface, planing, shoulder texturing, and pavement markings.
---------------------------------------
Van Zandt County
Weather permitting, Canton crews will begin base repair on FM 47. The work will be done south of US 80, near I-20. Expect lane closures with flaggers controlling traffic.
Van Zandt County construction projects updates:
FM 17, FM 47, and FM 859 Bridge Replacement
This project is for the construction of a new bridge and approaches, grading, base and surface, and metal beam guard fence installation. Work will resume in early January. Motorists should expect work zone speed limit reductions and shoulder width reductions on the I-20 main lanes. Motorists should also expect work zone speed limit reductions and shoulder width reductions on the I-20 frontage roads. Preparations are being made to close access to the FM 17 and FM 47 bridges for their demolition. The demolitions are scheduled to occur on Jan. 17 and 18 at night. Traffic will be detoured to the frontage roads. The bridge at FM 859 is open. Motorists should pay attention and travel with caution in the area.
FM 1255 Rehabilitate Existing Roadway
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Subgrade rehabilitation will be completed in one-mile segments. Crews are scheduled to remove trees in the right of way and install mailbox posts. Lane closures and speed reductions are expected. Motorists should expect delays.
I-20 WB Exit Ramp at SH 19
This project consists of ramp improvements. Crews have initiated construction on the drainage structures and frontage road alignment. Contractor is scheduled to continue cement treating the base. Lane closures and traffic shifts are expected.
FM 1651 Rehabilitate Existing Roadway-Tony
Construction is scheduled to resume the week of Jan. 20. Construction is on-going for the cross structures, driveways, and right of way clearing. The project is for the rehabilitation of the existing roadway, including widening, base repairs, signage, and striping. Subgrade work will be completed in one-mile segments. Lane closures and speed zone reductions are expected. Motorists should expect delays.
----------------------------------------
Wood County
This week, crews are scheduled to overlay on FM 852 west, from SH 11 to the Hopkins County line. Expect lane closures with flaggers controlling traffic. Crews are also scheduled to perform asphalt repair on SH 154 east of the SH 37 intersection in Quitman. Expect lane closures with flaggers controlling traffic.
Wood County construction projects updates:
US 69 Hot mix Overlay
This project consists of milling, level-up, surface repair, structures, signs, and pavement markings. Hot mix pavement operations are now underway. Crews are scheduled to work in the ditches, driveway installation, and striping. Lane closures are expected and speed limit reductions are in place. Motorists should expect delays.
US 69 Grade-Separated Interchange
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. Construction of the cross structures, drainage, and embankment is underway in the right of way. Motorists should be cautious of the large equipment traveling through the work zone. Lane closures are expected, and work zone speed reductions are in place. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract