05/29/2026 | Press release | Distributed by Public on 05/29/2026 13:54
St. Joseph, Mo. - The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in the Northwest Missouri region for the week of June 1-7.
There may be moving operations, such as mowing, brush cutting and litter removal, throughout the region in addition to the work mentioned below. Inclement weather may cause schedule changes in some of the planned work. Check the MoDOT Traveler Information Map at http://traveler.modot.org, or download the app for updated information.
MoDOT asks drivers to work with us by buckling up, putting your phone down, slowing down and moving over in work zones.
Atchison County
U.S. Route 136 - Resurfacing project from I-29 to U.S. Route 71 through August 2026. The road will be narrowed to one lane, and a 10-foot width restriction will be in place. (Contractor: Herzog Contracting Corp.)
Route J - Culvert replacement at 220th Street, June2.
Buchanan County
Gene Field Road Bridge - CLOSED for a bridge replacement project through July 2026. (Contractor: Clarkson Construction Company). https://www.modot.org/projects/gene-field-road-bridge-replacement-over-interstate-29-buchanan-county.
U.S. Route 59/Route 752/Route U - Intersection improvement project through spring 2027. (Contractor: Amino Bros. Co., Inc.) https://www.modot.org/projects/route-u-missouri-route-59-and-missouri-route-752-intersection-improvements-buchanan-county.
U.S. Route 169 - Intersection improvement project at Route FF through mid-August 2026. A 10-foot width restriction will be in place. Access to 49th Street will be closed through June 2026. (Contractor: Leavenworth Excavating & Equipment Company, Inc.)
U.S. Route 169 - CLOSED for an intersection improvement project at Southeast Riverside Terrace through mid-July 2026. (Contractor: Hoy Excavating, LLC) https://www.modot.org/projects/us-route-169-intersection-improvements-buchanan-county.
I-29 - Bridge approach repairs at the Pigeon Creek Bridge through early June 1-5. (Contractor: Herzog Contracting Corp.)
U.S. Route 169 - Scrub seal project, June 4-15. (Contractor: Vance Brothers, Inc.)
Caldwell County
Route 13 - Resurfacing from Route 6 in Gallatin to U.S. Route 36 in Hamilton through June 2026. Route 13 will be narrowed to one lane with flaggers. (Contractor: Herzog Contracting Corp.)
Route U - CLOSED at the Tom Creek Bridge, through mid-September 2026, for a replacement project. (Contractor: Decatur Bridge & Iron, LLC). https://www.modot.org/projects/route-u-bridge-replacement-caldwell-county-0
Route 116 - Concrete replacement from SW Lead Road to SW Ore Road, June 1-2.
Route 116 - Concrete replacement from Brangus Road to SW Gold Road, June 3-4.
Carroll County
Route 41 - CLOSED around-the-clock at the Wakenda Chute Bridge until further notice for bridge deck repairs.
Route 139 - ADA sidewalk improvements project in Hale, through early June 2026. (Contractor: Ti-Zack Concrete, LLC). https://www.modot.org/projects/missouri-route-139-route-cc-route-d-route-e-route-ee-route-m-and-route-k-sidewalkada
Route 24 - Scrub seal project, June 1-12. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers Inc.).
Route C - CLOSED for a culvert replacement from Route Z to County Road 201, June 2, 6 a.m. to 4:30 p.m.
Route NN - CLOSED for a culvert replacement from County Road 180 to County Road 160, June 3, 6 a.m. to 4:30 p.m.
Chariton County
Route K - ADA sidewalk improvements project in Keytesville, through June 2026. (Contractor: Ti-Zack Concrete, LLC). https://www.modot.org/projects/missouri-route-139-route-cc-route-d-route-e-route-ee-route-m-and-route-k-sidewalkada
Route M - ADA sidewalk improvements project in Mendon, through June 2026. (Contractor: Ti-Zack Concrete, LLC). https://www.modot.org/projects/missouri-route-139-route-cc-route-d-route-e-route-ee-route-m-and-route-k-sidewalkada
Route 11 - Scrub seal project, June 1-5. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers, Inc.)
Route F - Pothole patching from U.S. Route 24 to Route M, June 1-3.
Route F - Pothole patching from Route M to Route C, June 3-5.
Clinton Couty
I-35 - Pavement rehabilitation in the southbound lanes from Exit 40 (Lathrop) to Exit 48 (south Cameron) through September 2026. Both north and southbound traffic will be one lane, each direction, in the northbound lanes (Contractor: Michels Road & Stone). https://www.modot.org/projects/interstate-35-and-us-route-69-concrete-overlay-clinton-county.
I-35 - Bridge maintenance north and southbound near the 37.2 mile marker, June 2. A 10-foot width restriction will be in place.
Route U - CLOSED for a culvert replacement from NW Schwartz Road to NW Poage Road, June 3, 6:30 a.m. to 2:30 p.m.
Daviess County
Route 13 - Resurfacing and ADA improvements project from Berry Street to Van Buren Street in Gallatin through June 2026. Route 13 will be narrowed to one lane with flaggers. (Contractor: Herzog Contracting Corp.)
U.S. Route 69 - Scrub seal project, June 1-10. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers Inc.).
DeKalb County
Route 36 - intersection improvement project at Bob F. Griffin Road, through November 2026. (Contractor: Clarkson Construction Company).
Gentry County
Route C - Seal coat project from U.S. Route 136 to the Worth County line, June 1, 7 a.m. to 4 p.m.
Grundy County
Route O - pothole patching, June 1-5.
Linn County
Route C - CLOSED at the Long Branch Bridge, east of Purdin, for a bridge replacement project through the Northwest Bridge Bundle through October 2026. (Capital-Horner & Shifrin) *1
Route B - CLOSED at the Parsons Creek Bridge, west of Linneus, through June 2026. (Contractor: Louis-Company, LLC). https://www.modot.org/projects/route-b-route-e-and-route-u-bridge-deck-replacement-grundy-and-linn-counties-0
Mercer County
Route E - CLOSED at the West Medicine Creek Bridge through early June 2026 for a deck replacement project. (Contractor: E&C Bridge, LLC). https://www.modot.org/projects/route-e-route-ff-route-jj-and-route-oo-bridge-deck-replacement-multiple-counties.
Route D - CLOSED at the West Muddy Creek Bridge beginning through September 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
U.S. Route 136 - Bridge deck replacement project at the Grand River Overflow Bridge in Princeton, through early October 2026. The bridge will be narrowed to one lane with temporary traffic signals. (Contractor: Louis-Company, LLC). https://www.modot.org/projects/missouri-route-136-bridge-deck-replacement-mercer-county
U.S. Route 136 - ADA sidewalk improvements project in Princeton, through June 2026. (Contractor: Ti-Zack Concrete, LLC).
Nodaway County
U.S. Route 71 - Resurfacing project from the Iowa state line to U.S. Route 136 near Burlington Junction through August 2026. The road will be narrowed to one lane, and a 10-foot width restriction will be in place.
U.S. Route 136 - Resurfacing project from I-29 to U.S. Route 71 through August 2026. The road will be narrowed to one lane, and a 10-foot width restriction will be in place.
Hawk Road/U.S. Route 71 - access to Hawk Road CLOSED at U.S. Route 71 for bridge barrier work and guardrail replacement June 1-20. U.S. Route 71 will also be narrowed to one lane with temporary traffic signals at the White Cloud Creek Bridge.
Route U - CLOSED until further notice from northbound U.S. Route 71 to Jet Road.
Route 136 - Shoulder work from U.S. Route 71 to Route 113, June 3.
Putnam County
Route N - CLOSED at the Turkey Creek Bridge through July 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route 5 - Resurfacing project from U.S. Route 136 east of Unionville to Route 6 north of Milan through July 2026. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Emery Sapp & Sons, Inc.).
Sullivan County
Route PP - CLOSED at the West Locust Creek Bridge through June 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route T - CLOSED at the East Locust Creek bridge through July 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route 5 - Resurfacing project from U.S. Route 136 east of Unionville to Route 6 north of Milan through July 2026. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Emery Sapp & Sons, Inc.).
Route 129 - CLOSED at the Spring Creek Bridge through August for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route OO - CLOSED at the Locust Creek Bridge through mid-August 2026 for a deck replacement project. (Contractor: E&C Bridge, LLC). https://www.modot.org/projects/route-e-route-ff-route-jj-and-route-oo-bridge-deck-replacement-multiple-counties
Route B - CLOSED between Route M and Old Route VV, June 2-3, 7:30 a.m. to 3 p.m. daily.
Route B - CLOSED between Old Route VV and Route N, June 4-5, 7:30 a.m. to 2 p.m. daily.
Worth County
Route C - Seal coat project from Route 46 to Route M, June 1, 7 a.m. to 4 p.m. The road will be narrowed to one lane with flaggers guiding motorists through the work zone and a 10-foot width restriction.
Route D - Seal coat project from Route M to Route U, June 2-3, 7 a.m. to 4 p.m. daily. The road will be narrowed to one lane with flaggers guiding motorists through the work zone and a 10-foot width restriction.
Route U - Seal coat project from Route M to the Iowa state line, June 2-3, 7 a.m. to 4 p.m. The road will be narrowed to one lane with flaggers guiding motorists through the work zone and a 10-foot width restriction.
---
*1 This bridge is part of the NWBB (Northwest Bridge Bundle) program. The design-build team is Capital-Horner & Shifrin. More info: NWBB program web page.
*2 These bridges are part of the Safe and Sound Bridge Rehabilitation program. The contractor is Capital Paving & Construction, LLC. A full listing of bridges and project information can be found at: https://www.modot.org/projects/northwest-missouri-safe-sound-bridge-rehabilitations.
*3 In 2024, the Governor signed the Fiscal Year 2025 budget, including an additional $100 million to continue low-volume road improvements. This funding will be used to improve conditions on 1,985 lane miles of rural roads at 149 locations, including the ones listed below. For more information on the Governor's Rural Roads Program, visit: https://www.modot.org/governors-rural-routes-program.
###