MoDOT to narrow eastbound I-70 lanes between Warrenton and Foristell

WARREN COUNTY - The Missouri Department of Transportation will begin narrowing eastbound Interstate 70 lanes in two locations between Warrenton and Foristell as part of the Improve I-70 Warrenton to Wentzville Project. All work is weather permitting and schedules are subject to change.

Traffic impacts on eastbound I-70 will include the following:

  • Wright City to St. Charles County Line (mile marker 200.8 to 203)
    • Starting April 17 through September 2025 - Nightly right lane closures 8:00 PM to 6:00 AM
    • Non-working hours: traffic will be shifted into narrower lanes with barrier wall along the right shoulder.
  • East of Route 47 to the Wright City Rest Area (mile marker 194.2 to 197.6)
    • Starting the week of April 28 through September 2025 - Nightly right lane closures 8:00 PM to 7:00 AM
    • Non-working hours: traffic will be shifted into narrower lanes with barrier wall along right shoulder.
  • I-70 eastbound on-ramp at Wright City (Exit 200)
    • April 22 & 23 - Nightly ramp closures from 7:00 PM to 4:00 AM

The Improve I-70: Warrenton to Wentzville is the second project in MoDOT's Statewide Improve I-70 Program and will add a third lane of travel in each direction to I-70 from Warrenton to Wentzville. The project includes the Improve I-70 funding and additional legislatively designated General Revenue funding. It also includes previously allocated funds in the state's program for other I-70 and I-64 projects, for a total contract of $600 million.

Missouri's FY2024 budget, approved through the state legislative process and signed into law by the governor, provides $2.8 billion in General Revenue to build a third lane of I-70 across the state. The program will plan, design, construct, reconstruct, rehabilitate, and add a third lane in each direction on nearly 200 miles of I-70, from Blue Springs to Wentzville. For more information on the Improve I-70 Program and to sign up for program e-mails, visit http://www.modot.org/improvei70 .

For more information, call MoDOT at 888-ASK-MODOT (275-6636) or visit www.modot.org . To receive the latest statewide news and text alerts, signup for e-updates .

MoDOT - Missouri Department of Transportation published this content on April 11, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on April 11, 2025 at 18:03 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]