Phase 1 of Boyson Road Patching Project Completed; Work Begins on Phase 2

This afternoon, Friday, Aug. 22, crews are expected to complete Phase 1 of the Boyson Road Patching Project and switch traffic control to Phase 2.

Phase 1 included over 2,000 square yards of full depth patches, 1,600 square feet of partial depth patches, 92 cross-stitched tie bars, diamond grinding of the pavement surface, crack sealing and pavement markings.

Phase 2 will close Boyson Road from Alburnett Road to Central Avenue. The current detour, which uses C Avenue, Tower Terrace Road and Alburnett Road will remain in place with specific modifications for Phase 2. Residents on Timber Oak Court and in the Bowman Meadows subdivision will have access from the west via Bowman Meadows Drive during Phase 2.

Phase 2 is expected to last 4 weeks, weather permitting.

Questions may be directed to the Public Works Department at 319-743-6340.


City of Marion, IA published this content on August 22, 2025, and is solely responsible for the information contained herein. Distributed via Public Technologies (PUBT), unedited and unaltered, on August 22, 2025 at 18:08 UTC. If you believe the information included in the content is inaccurate or outdated and requires editing or removal, please contact us at [email protected]