02/27/2026 | Press release | Distributed by Public on 02/27/2026 14:10
Where : North and southbound U.S. Route 65 to westbound I-44 (Exit 82) ramps CLOSED in Springfield
When: 8 p.m. Friday, February 27 until 6 a.m. Saturday, February 28
What: Contractor crews will close the north and southbound U.S. Route 65 to westbound I-44 (Exit 82) ramps to pave a layer to cover the newly laid rock base.
This closure is in addition to the upcoming ramp CLOSURES on March 2-13 for the new ramp pavement installation. However, if the March 2-13 work is delayed due to weather, an updated schedule will be released as soon as it's available. This work is part of the Forward 44: Springfield Improvements in Greene County project. Detour for these ramp closures include eastbound I-44 to Missouri Route 744/Mulroy Road/Beaver Road.
Traffic Impacts:
Weather and/or construction delays will alter the work schedule .
Project Summary:
Contractor: Capital Paving & Construction LLC, Jefferson City
The awarded construction cost is $70.7 million, including $13.4 million in General Revenue funds provided by the General Assembly and the Governor's Office.
To get project updates or sign up for project emails, visit https://www.modot.org/projects/forward-44-springfield-improvements.
The project is scheduled for completion in May 2027.
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest