Buffalo Speedway Paver Repairs

Beginning January 13, Gulf Coast Pavers will begin phased repairs on the Buffalo Speedway brick paver crosswalks and intersection logos. The project is expected to last approximately 90 days, with work completed in three phases to minimize disruptions and ensure efficient progress.

Phase 1: Crosswalks on Buffalo Speedway (East and West)

  • Locations: Sunset Blvd., Rice Blvd., and University Blvd.
  • Work will start in the left-hand turn lane and move outward east and west to maintain consistent paver patterns.
  • Duration: Estimated 3 weeks per location (Weather Permitting)

Phase 2: Intersection Crosswalks (North and South)

  • Locations: Sunset Blvd., Rice Blvd., University Blvd., and W. Holcombe Blvd.
  • Crews will work on intersection crosswalks while Buffalo Speedway remains open.
  • Duration: Estimated 6 days per location (Weather Permitting)

Phase 3: Intersection Logos

  • Locations: Sunset Blvd., Rice Blvd., and University Blvd.
  • Work will occur in three stages: left-turn lanes, inner lanes, and outer lanes.
  • Duration: Estimated 6 weeks per location (Weather Permitting)

Temporary traffic control measures will be in effect during each phase. Drivers and pedestrians should exercise caution near work zones and follow all posted signs. We kindly ask drivers to plan their routes accordingly, as temporary delays may occur in these areas.

If you have questions about this project, please contact Capital Projects Manager, Eduardo Barreto by email at [email protected] or by phone at 713-662-5848.