W. Club Boulevard Corridor Utility Rehabilitation Project Two-Week Look Ahead
September 27, 2025
The City appreciates your ongoing patience with the work associated with this project. Additional information regarding this project can be found at: www.durhamnc.gov/3705.
The contractor, Moffat Pipe, Inc., has completed work on Ninth Street between Safeway and W. Knox streets. This roadway is no open with no detours.
Here's the two-week look ahead for this project. Please note that this work schedule may be affected by weather.
September 29-October 3, 2025
Crews 1 & 2 - Both crews will be working on W. Club Boulevard between Alabama Avenue and Maryland Avenue to install water services on both sides of W. Club Boulevard.
October 6-10, 2025
Crews 1 & 2 - Both crews will be working on W. Club Boulevard to install water services. Waterline installation work on Oakland Avenue is anticipated to begin on Thursday, October 9.
Road closure information
An active temporary road closure remains in place on W. Club Boulevard between Alabama Avenue and Maryland Avenue.
Project contacts:
Wade Tong, Construction Team Manager, City of Durham, [email protected]
Zeke Urias, Project Manager, Moffat Pipe Inc., [email protected]